Phase 0: Assessment
Objective
Fulfill requirement to submit capital planning investments through Capital Planning and Investment Control (CPIC) process with required additional information.
Key Tasks
Program Management
Define Vision
Responsible Party
customerInputs
- Government-wide Standards defined through the FIBF website
Outputs
- Vision Statement
- In-scope Service Area(s) and Function(s)
- Expected Benefits
- High Level Timelines
Develop Project Business Case
Responsible Party
customerInputs
- Vision Statement
- In-scope Service Area(s) and Function(s)
- Expected Benefits
- High Level Timelines
- Government-wide Standards defined through the Federal Integrated Business Framework (FIBF) website
- Capital Planning and Investment Control (CPIC) Guidance
Outputs
- Project Business Case
- Investment Readiness Checklist
Workforce, Organization, and Stakeholders
Technology
Process and Service Delivery
Exit Criteria (to move into Phase 1)
- In-Scope Service Area(s) and Function(s)
- Steering Committee Review of Project Business Case
- Vision Statement, Expected Benefits, and High Level Timelines
Phase 0 Examples:
M3 Examples MAX PagePhase 0 Documentation
The following documentation is developed during Phase 0, follows Federal CPIC requirements, and is used to inform a review, if necessary. Agencies should follow CPIC guidance to develop these outputs. Agencies purchasing transaction processing services only will identify relevant activities and examples for their project using the M3 Services Tailoring Guide.
- Investment Readiness Checklist
- Project Business Case
- Vision Statement
Navigate to OMB CPIC Guidance to complete the Project Business Case.