M3 Playbook > Phase 4: Migration > 4.17 Develop and Execute Cutover Plan for Go-Live
Play Icon

4.17 : Develop and Execute Cutover Plan for Go-Live

Technology
  1. Shared

    Develop Cutover Plan to include pre cutover, cutover, and post cutover steps

  2. Shared

    Integrate Cutover Plan with overall communication & program Go-Live schedule

  3. Shared

    If Go decision made-execute Cutover Plan & monitor activities towards deployment

  4. Shared

    If No-Go decision made-execute Contingency Plan procedures

  5. Shared

    Communicate cutover activities to stakeholders

  6. Shared

    Execute pre cutover tasks

  7. Shared

    Schedule checkpoints to monitor Go-Live progress

  8. Provider

    Execute cutover - deploy code, activate system components, transition/retire legacy IT

  9. Provider

    Initiate post cutover activities to include warranty period support

  10. Customer

    Update decommission plan for legacy systems

4.17 Lessons Learned

  • Establish an ongoing and committed contact center support at each organization to help facilitate Go-Live transition
  • Have all key Subject Matter Experts (SMEs) available onsite during final pilot trial and actual deployment
  • Conduct daily meetings to monitor progress and issues for timely resolution
  • Use the Cutover Plan to define cutover communication steps and checkpoint meetings, align resources, and identify risks with aligned contingency plans in place. Determine activities for before, during, and after the day of cutover

Stakeholders

Recommended stakeholders, inputs, & outputs may vary by implementation; however, agencies that contributed to this Playbook reported these factors as increasing the likelihood of success.

Customer

  • Program Manager
  • Functional Lead
  • Technical Lead / Solution Architect
  • Security Lead
  • Network SME
  • PMO Lead
  • PMO Team
  • Change Management Lead
  • Communications Lead
  • Data Conversion Lead
  • Interface Lead

Provider

  • Program Manager
  • Functional Lead
  • Technical Lead / Solution Architect
  • Security Lead
  • Network SME
  • PMO Lead
  • PMO Team
  • Change Management Lead
  • Communications Lead
  • Data Conversion Lead
  • Interface Lead

Inputs

Outputs

  • Cutover Plan
  • Decommission Plan